Owner
Lexis Nexis
Mechanical Contractor
Batchelor and Kimball
Construction
Cost
$300,000
 |
Scope
Mechanical systems design and construction phase
services for a new water storage system and modifications to the
cooling tower make-up water system to enhance reliability.
Special
Circumstances
-
Add
two 20,000 gallon, vertical aboveground water tanks to hold
standby make-up water.
-
Modify the existing water system to allow a domestic water to
blend with well water stored in the new water storage tanks.
-
Provide new, redundant, make-up water pumps.
-
Modify existing control system to accommodate new water storage
tanks and make-up water system.
-
Integrate new storage system with existing system, with minimum
interruption of service.
-
Permit variable blending of domestic and well supplied water
into the new storage system.
|